Pardon Our Dust

Construction Notice

The Carlsbad Inn will be undergoing several major construction projects. The largest of these scheduled projects is the Waterproofing of the Garage, which is scheduled to begin mid-March of 2019 and take place through the Spring of 2021. You may view a color-coded map of planned renovation phases HERE. 

 


There are 5 phases to this construction project, which include:

 

  • Mar 2019-May 2019: Elm Building corridor Demo & Re-Build, N/W sides of Elm Waterproofing

 

  • June 2018-August 2019: Garage Drain lines & Column Repairs

 

  • Sept 2019-May 2020: Pool Demo, East side of Elm Building & street side of Elm

 

  • Nov 2019-May 2020: Pool Re-Build, East Side of Oak & street side of Oak

 

  • Sept 2020-May 2021: Oak Corridors, Oak Perimeters, & Courtyard

 


As with all construction projects, the timeline may fluctuate. Please visit this page often for weekly updates, images of the planned improvements, and before-and-after photos. Architectural renderings are available HERE. They are also displayed in the Front Lobby of Carlsbad Inn.